Close cookie policy popup window
This site uses cookies for analysis purposes only. This helps us understand how you and other visitors use our site. To see a complete list of these cookies or to opt out please access our cookie policy page.

You will see this message only once, but you will be able to find more information about our use of cookies or opt out at any time.
Case Study - Project Management and CDM Co-Ordination - Cheshunt School

Case Study - Project Management & CDM - Cheshunt

Published on Monday, 01 January 0001

CHESHUNT SCHOOL REFURBISHMENT OF REDUNDANT MACHINE WORKSHOP TO NEW DRAMA STUDIO & IT SUITE

Client:    The Governors of Cheshunt School, Cheshunt School, College Road, Cheshunt, EN8 9LY.

Testimonial:  

Head Teacher of Cheshunt School, Steve Drake, reports that their new Drama Studio and IT Suite will add tremendous value to both teaching and learning across the school.

Mr Drake added; “Kirkby & Diamonds management and careful programming of works minimised the disruption to the school throughout the duration of the project. The personalised service we received from the K&D Team ensured the building works were completed on time and within budget. The qualities of the new Drama Studio and IT Suite and the service we have had from K&D have exceeded our expectation, and we hope to work with them again on future schemes”.

Start Date:        July 2009

Completion:    September 2009

Value:               £100,000

Description:   

The project involved taking an old wood and metal machine workshop, which had been decommissioned and was not being utilised by the school, and refurbishing the building as a whole to provide a new teaching facility.

Works included internal and external insulating of the building, replacement of the dated electrical installation and upgrading of lighting, heating and introduction of IT services.

The internal layout of the building had minor reconfiguration to provide a soundproofed drama studio with sprung dance floor and mirrored wall, and a small IT suite to be used for the editing of media productions.

Role:   

Project Management and CDM Co-ordination. Specific duties include overall cost control, client liaisons, procurement advice and contract administration.

Procurement Route / Contract type:

JCT 2005 – Minor works building contract.

Architect:    Bob Harrington Design Ltd.